One Intelligent Digitized New Material Project Cement Production Line Waste Heat Power Generation Project Successfully Connects to Grid

PublishDate:2024-06-12 Source:


   

  Recently, the first phase of 6000t/d cement production line waste heat power generation project of Jiangshan Green Intelligent Digitalized New Material Project, general contracted by Sinoma Energy Conservation, has been successfully connected to the grid.

  圖片
 

  The project is located in the High-Tech Park of Jiangshan Economic Development Zone, Zhejiang Province, and the scope of work includes design, supply & system commissioning work. The contract was signed on May 31, 2023, the timer started on June 15, 2023, and on June 9, 2024, the unit was completed and connected to the grid for power generation.

   

  After the signing of the contract, in order to ensure that the project generates electricity as scheduled, the project department of Sinoma Energy Conservation Engineering Subcontracting Company carefully planned the work arrangement of each stage. In the preliminary preparation stage, the project department actively coordinated with various departments to complete the basic design and procurement work in time; in the installation and commissioning stage, all the members of the project department overcame all kinds of difficulties and stood firm at the construction site, which ensured that the project reached the project nodes according to the contract as scheduled.

   

  The project's waste heat power station has an installed capacity of 12MW, adopts the newly developed fourth generation cement waste heat power generation technology, and realizes a high degree of integration between the cement waste heat power generation system and clinker line. In the AQC system, the closed cycle of waste air is adopted, and the air cooler and chimney at the kiln head are eliminated, which effectively improves the efficiency of waste heat utilization under the premise of ensuring the clinker strength and cooling effect. The kiln tail adopts low resistance and high efficiency SP waste heat boiler, which improves the heat exchange effect and reduces the boiler resistance, and lowers the power consumption of the firing system. Electric and pneumatic valves are widely used in the power station system, and the logic control is written in accordance with the start-stop sequence of the power station, which can realize one-key start-stop and full-automatic operation of the whole power station system.

   

  This project not only improves the economic benefits of the enterprise, but also reduces environmental pollution, improves the energy utilization rate, and makes a positive contribution to the local realization of the 'double carbon' goal.

   

   

主站蜘蛛池模板: 成年人黄色大片| 日本高清二三四本2021| 国产丝袜制服在线| 亚洲第一伊人| 一级香蕉视频在线观看| 欧美一级高清在线观看| 性殴美| 国产亚洲人成网站在线观看| 午夜精品久久久久久影视riav | 国产又色又爽又黄又刺激18| 亚洲福利视频在线| 91天天射| 久久久久无码国产精品一区| 亚洲一在线| 好吊妞gao988在线播放| 国产一级不卡毛片| 国产精品 主播精选 网红| 精品国产区一区二区三区在线观看| 国内自拍第1页| 亚洲国内精品久久| a性片| 曰本一级毛片免费| 成人毛片18岁女人毛片免费看| 欧美亚洲三级| 国产一区视频在线| 国产啪在线| 草在线视频| 美女视频毛片| 韩国r级福利视频在线观看网站| 成人影院午夜久久影院| 欧美久在线观看在线观看| 亚欧在线精品免费观看一区| 亚洲综合网在线| 18日本xxxxxxⅹxx96| 日本一级特黄毛片高清视频| 亚洲一级毛片欧美一级说乱| 亚洲精品国产一区二区| 成年女人在线观看| 男女做a一级视频免费观看| 直接看的黄色网址| 青青青青操|